Home / Tooling Delays Cost Auto Industry $1.7 Billion

Tooling Delays Cost Auto Industry $1.7 Billion

This is the equivalent of 80 tool & die shops sitting idle at any given time, placing almost 15 percent of annual business in the industry on hold.

Posted: July 2, 2015

The Original Equipment Suppliers Association (OESA; Troy, MI) and Harbour Results Inc. (HRI; Troy, MI), recently completed the third Automotive Tooling Barometer (also known as “The Barometer”) to better understand the impact and cause of automotive program delays. The Barometer indicates that 66 percent of tool shops had more than half of their projects over the past four months delayed two weeks or more.

On an annualized basis, almost 15 percent of business is on hold. Based on the size of the tool and die industry, that translates to $1.7 billion, or the equivalent of 80 tool shops, sitting idle at any given time.

The leading drivers of program delays were noted as late changes in design and processes based on manufacturing, mold or tool-build feasibility, or changes reflecting cost saving activities. These concessions were driven by design feasibility and formability issues, which could have been avoided with better engineering and up-front work. Additionally, the lack of purchase orders is another cause of program delays, with nearly 25 percent of respondents indicated this as the leading cause.

“Capacity planning can be challenging for tool and die shops due to many factors such as long lead times, lack of data and, most critically, program delays. It makes it difficult to run a business profitability when you can’t consistently predict staffing, machine use or raw material needs,” said Laurie Harbour, the president and chief executive officer of HRI. “It is our goal with The Barometer to provide accurate data and information to help the tool and die industry better manage these issues.”

The Barometer also showed a collective Tooling Sentiment Index (TSI) of 56, indicating a positive outlook for the automotive tooling supplier industry. Of the respondents, 35 percent indicated a significantly or somewhat more optimistic view of the 12-month outlook whereas only 17 percent of respondents indicated some level of pessimism. Pessimism stemmed primarily from the before mentioned program delays.

“With all the concern over constraints in the tooling industry, the Tooling Barometer’s identification of idle time, its cause and effect, is staggering,” said Margaret Baxter, the OESA senior vice president of operations and international affairs. “We are making strides in identifying and understanding the issue, but it will take the entire value chain working together to address program delays and holds.”

www.harbourresults.com

Subscribe to learn the latest in manufacturing.

Calendar & Events
Southeast Design – 2-Part Show
September 11 - 12, 2013
Greenville, SC
Mid-Atlantic Design – 2-Part Show
September 25 - 26, 2013
Phoenixville, PA
CMTS of Canada
September 30 - October 3, 2013
Mississauga, Canada
DISCOVER 2013
October 8 - 16, 2013
Florence, KY
Wisconsin Manufacturing and Technology Show
October 8 - 10, 2013
Wisconsin State Fair Park Exposition Center Halls B&C
WESTEC 2013
October 15 - 17, 2013
Los Angeles, CA
SOUTH-TEC
October 29 - 31, 2013
Greenville, SC
New England Design-2-Part Show
October 30 - 31, 2013
Marlborough, MA
DMG / Mori Seiki Manufacturing Days
November 12 - 15, 2013
Mori Seiki Manufacturing – Davis, CA
FABTECH
November 18 - 21, 2013
McCormick Place – Chicago, IL
Midwest Design-2-Part Show
November 20 - 21, 2013
Northern Kentucky Convention Center – Covington, KY
PCD Tool Manufacturing
November 20, 2013
United Grinding North America – Fredricksburg, VA